Quick answer: Designing for 100kW+ racks means coordinating electrical capacity, liquid cooling, residual air cooling, structural loading and maintenance access around a specific server configuration. A rack power figure is only a starting point. Validate the complete path from utility supply and heat rejection to rack connections, including operation during planned maintenance and agreed failure scenarios.

High-density rack design concentrates infrastructure demands into a small area. A hall can have adequate total power and cooling yet lack enough capacity along the particular electrical and hydraulic routes serving a GPU cluster. Successful design therefore starts with the rack and follows every supporting system outward.
Use a real hardware specification
NVIDIA’s DGX GB200 documentation describes an NVL72 configuration with approximately 120kW rack consumption. This is a concrete example of the density involved, not a universal rating for AI racks. Different platforms and configurations require their own design data. NVIDIA rack hardware guide
Obtain the approved rack configuration, power requirements, cooling specifications, operating weight and service clearances. Confirm which values are maximum requirements, which describe typical operation and which depend on the installed equipment. Document the revision used for design.
If the IT purchase is still being finalized, state the permitted equipment envelope and identify the decisions that cannot be released until the configuration is confirmed. Avoid promising compatibility with an unspecified future GPU generation.
Trace electrical capacity to the rack
Map the supply from the site connection through transformers, switchgear, UPS systems and distribution equipment to the rack inputs. Check capacity at each stage under the required operating conditions. A sufficient campus allocation does not demonstrate that a particular row can support its planned deployment.
Clarify the rack’s input arrangement and the intended response when a supply path is unavailable. Equipment redundancy within a rack should not be assumed to provide redundancy in the facility distribution. Have the electrical design team verify protection, loading and the relevant equipment requirements.
For an illustrative row of eight racks at 120kW each, the rack load totals 960kW before other loads and design allowances. That arithmetic establishes a planning input; it is not a complete switchboard, utility or backup-power sizing calculation. Apply the selected design criteria to the actual equipment and operating cases.
Separate liquid and air heat loads
Ask the hardware supplier how much heat reaches the liquid circuit and how much is released to air. The split varies by system. Do not automatically apply a percentage from one rack platform to another.
Size the technical cooling circuit using the specified temperatures, fluid properties, flow and pressure requirements. Then confirm that the CDU and facility loop can transfer the required heat under the same conditions. Nameplate capacity alone is insufficient if the quoted rating assumes a different temperature difference.
Residual room heat still needs an air path and a heat-removal strategy. Review airflow, containment and local air-cooling capacity around the installed racks. Also consider adjacent network equipment and other devices outside the liquid-cooled portion of the cluster.
Coordinate the main design interfaces
|
Interface |
Information required |
Design question |
|
Rack electrical input |
Approved supply and load specification |
Can each required operating case be supported? |
|
Rack liquid connections |
Temperature, flow, pressure and fluid limits |
Do the rack and distribution system agree? |
|
Residual air load |
Heat released to the room |
Can the local air system remove it? |
|
Structural support |
Operating and transport loads |
Can the floor and delivery route support them? |
|
Service area |
Removal paths and clearances |
Can equipment be maintained after installation? |

Treat warm-water operation as a verified option
Where the hardware supports it, warmer coolant can influence the choice of heat-rejection equipment and operating strategy. EPG’s Cooling Solution includes warm-water and hybrid air–liquid arrangements. Confirm the actual server inlet requirement before adopting a 45°C design target.
Record the temperatures on both sides of each heat exchanger. Ask the mechanical team to demonstrate performance across the applicable climate conditions and maintenance configurations. Include any required supplemental cooling and the energy used by the complete system.
Plan monitoring points so operators can distinguish a facility-side issue from a rack-side issue. Agree the measurements and alarm responses with the equipment suppliers, including who responds when the rack reports a thermal limitation.
Check the physical deployment route
Validate floor loading, equipment dimensions, access doors, lifting arrangements and the route from delivery to final position. Use the fully configured rack weight and consider temporary handling conditions, rather than relying only on an empty rack specification.
Coordinate liquid pipework, power distribution and network routes in one layout. Connections need accessible isolation points and enough working space for service. An arrangement that fits on a drawing may obstruct component removal once all systems are installed.
For phased growth, identify where additional connections will be made and how later work will be separated from operating equipment. Reserve space only where the expansion plan justifies it, and document any future work that would require an interruption.
Commission the integrated installation
Agree test procedures before equipment arrives. Demonstrate the required electrical and thermal performance, controls integration and response to the selected maintenance and failure scenarios. Confirm which conditions can be reproduced with temporary loads and which need final IT validation.
Include operators in the handover. They need accurate equipment identification, operating procedures, escalation routes and records of the accepted configuration. A successful test is more useful when the operating team understands what was demonstrated and what limitations remain.
Build around a coordinated design basis
EPG’s AIDC Solution provides a starting point for modular AI infrastructure discussions, while its IDC Solution addresses facility integration. Bring the rack specification, site constraints and phased capacity plan together so power, cooling and physical installation can be reviewed as one project.