  • Designing for 100kW+ Racks: Power and Cooling for GPU Clusters

    Designing for 100kW+ Racks: Power and Cooling for GPU Clusters

    Quick answer: Designing for 100kW+ racks means coordinating electrical capacity, liquid cooling, residual air cooling, structural loading and maintenance access around a specific server configuration. A rack power figure is only a starting point. Validate the complete path from utility supply and heat rejection to rack connections, including operation during planned maintenance and agreed failure scenarios.

    Server racks and aisle infrastructure in a data center

    High-density rack design concentrates infrastructure demands into a small area. A hall can have adequate total power and cooling yet lack enough capacity along the particular electrical and hydraulic routes serving a GPU cluster. Successful design therefore starts with the rack and follows every supporting system outward.

    Use a real hardware specification

    NVIDIA’s DGX GB200 documentation describes an NVL72 configuration with approximately 120kW rack consumption. This is a concrete example of the density involved, not a universal rating for AI racks. Different platforms and configurations require their own design data. NVIDIA rack hardware guide

    Obtain the approved rack configuration, power requirements, cooling specifications, operating weight and service clearances. Confirm which values are maximum requirements, which describe typical operation and which depend on the installed equipment. Document the revision used for design.

    If the IT purchase is still being finalized, state the permitted equipment envelope and identify the decisions that cannot be released until the configuration is confirmed. Avoid promising compatibility with an unspecified future GPU generation.

    Trace electrical capacity to the rack

    Map the supply from the site connection through transformers, switchgear, UPS systems and distribution equipment to the rack inputs. Check capacity at each stage under the required operating conditions. A sufficient campus allocation does not demonstrate that a particular row can support its planned deployment.

    Clarify the rack’s input arrangement and the intended response when a supply path is unavailable. Equipment redundancy within a rack should not be assumed to provide redundancy in the facility distribution. Have the electrical design team verify protection, loading and the relevant equipment requirements.

    For an illustrative row of eight racks at 120kW each, the rack load totals 960kW before other loads and design allowances. That arithmetic establishes a planning input; it is not a complete switchboard, utility or backup-power sizing calculation. Apply the selected design criteria to the actual equipment and operating cases.

    Separate liquid and air heat loads

    Ask the hardware supplier how much heat reaches the liquid circuit and how much is released to air. The split varies by system. Do not automatically apply a percentage from one rack platform to another.

    Size the technical cooling circuit using the specified temperatures, fluid properties, flow and pressure requirements. Then confirm that the CDU and facility loop can transfer the required heat under the same conditions. Nameplate capacity alone is insufficient if the quoted rating assumes a different temperature difference.

    Residual room heat still needs an air path and a heat-removal strategy. Review airflow, containment and local air-cooling capacity around the installed racks. Also consider adjacent network equipment and other devices outside the liquid-cooled portion of the cluster.

    Coordinate the main design interfaces

    Interface

    Information required

    Design question

    Rack electrical input

    Approved supply and load specification

    Can each required operating case be supported?

    Rack liquid connections

    Temperature, flow, pressure and fluid limits

    Do the rack and distribution system agree?

    Residual air load

    Heat released to the room

    Can the local air system remove it?

    Structural support

    Operating and transport loads

    Can the floor and delivery route support them?

    Service area

    Removal paths and clearances

    Can equipment be maintained after installation?

    Illustration of a liquid-cooled modular data center

    Treat warm-water operation as a verified option

    Where the hardware supports it, warmer coolant can influence the choice of heat-rejection equipment and operating strategy. EPG’s Cooling Solution includes warm-water and hybrid air–liquid arrangements. Confirm the actual server inlet requirement before adopting a 45°C design target.

    Record the temperatures on both sides of each heat exchanger. Ask the mechanical team to demonstrate performance across the applicable climate conditions and maintenance configurations. Include any required supplemental cooling and the energy used by the complete system.

    Plan monitoring points so operators can distinguish a facility-side issue from a rack-side issue. Agree the measurements and alarm responses with the equipment suppliers, including who responds when the rack reports a thermal limitation.

    Check the physical deployment route

    Validate floor loading, equipment dimensions, access doors, lifting arrangements and the route from delivery to final position. Use the fully configured rack weight and consider temporary handling conditions, rather than relying only on an empty rack specification.

    Coordinate liquid pipework, power distribution and network routes in one layout. Connections need accessible isolation points and enough working space for service. An arrangement that fits on a drawing may obstruct component removal once all systems are installed.

    For phased growth, identify where additional connections will be made and how later work will be separated from operating equipment. Reserve space only where the expansion plan justifies it, and document any future work that would require an interruption.

    Commission the integrated installation

    Agree test procedures before equipment arrives. Demonstrate the required electrical and thermal performance, controls integration and response to the selected maintenance and failure scenarios. Confirm which conditions can be reproduced with temporary loads and which need final IT validation.

    Include operators in the handover. They need accurate equipment identification, operating procedures, escalation routes and records of the accepted configuration. A successful test is more useful when the operating team understands what was demonstrated and what limitations remain.

    Build around a coordinated design basis

    EPG’s AIDC Solution provides a starting point for modular AI infrastructure discussions, while its IDC Solution addresses facility integration. Bring the rack specification, site constraints and phased capacity plan together so power, cooling and physical installation can be reviewed as one project.

  • AI Data Center Power Planning for Grid Capacity and Phased Expansion

    AI Data Center Power Planning for Grid Capacity and Phased Expansion

    Quick answer: AI data center power planning must address both the electricity available to a site and the infrastructure that delivers it to compute racks. Grid connection timing can constrain expansion, while denser AI systems place new demands on distribution and cooling. Phased deployment and emerging 800V DC architectures address different parts of this challenge and should be evaluated together.

    Server racks and aisle infrastructure in a data center

    An AI data center can have space for more servers and still lack the power needed to operate them. The limiting factor may be the date when additional grid capacity becomes available, the rating of an electrical distribution path or the cooling capacity serving a particular row.

    The IEA’s 2026 report on energy and AI examines growing electricity demand alongside the ability of grids and equipment supply chains to respond. For project developers, this makes power availability an early site-selection and scheduling consideration. IEA energy and AI analysis

    A successful power plan needs to connect the utility commitment to capacity that can actually be commissioned and operated at each stage.

    Start with available capacity and connection timing

    A proposed campus capacity is different from an energized connection. Before setting a launch date, establish the capacity the utility can supply, the conditions attached to that supply and the works required to make it available.

    The programme should identify dependencies such as substation completion, transformer delivery and connection testing. Treat unconfirmed expansion capacity separately from the supply available for the first operational phase.

    Consider a project intended to expand over several years. If the initial connection supports only part of the final development, the first phase needs its own workable power and cooling arrangement. Installing every rack at the outset would leave some equipment waiting for the supporting infrastructure.

    Separate IT demand from total facility demand

    Server demand is only part of the electrical requirement. Cooling equipment, power-conversion losses and other facility services also consume energy.

    For an illustrative energy budget, 10 MW of average IT demand at an average power usage effectiveness, or PUE, of 1.20 corresponds to 12 MW of average facility demand. This is an energy-planning example, not a rating for a utility connection or switchboard. Equipment sizing also requires peak-load calculations, operating margins and the intended maintenance and failure conditions.

    The same distinction applies within the data hall. An acceptable average rack density can conceal a row whose local distribution capacity is insufficient. Map rack demand to the actual feeders, busways and cooling systems that serve it.

    Understand where 800V DC fits

    Higher-voltage direct-current distribution is attracting attention as AI racks become more power-intensive. At a given DC power level, increasing voltage reduces current. This can reduce conductor requirements, subject to the complete electrical design and protection requirements.

    NVIDIA’s August 2026 road-map describes an 800V DC power rack arriving in the second half of 2026, with a row power center expected in 2027. The architecture is intended to simplify power conversion and support denser compute. These are vendor road map statements, so procurement plans should confirm actual availability and compatibility. NVIDIA 800V DC roadmap

    For an operator, 800V DC is a distribution decision. It can improve how electricity reaches the racks, but it does not increase the capacity granted by the utility. Engineers must also consider DC protection, isolation, compatible IT equipment and maintenance procedures. NVIDIA architecture overview

    Integrated cooling infrastructure serving a data center

    Phase power and cooling together

    Phased data center deployment can align investment with available power and expected IT demand. Each phase should include enough electrical and thermal infrastructure to operate independently within its design limits.

    Future expansion also needs physical provision. Reserve space and routes for additional equipment, define connection points and establish how new systems will be tested beside operating capacity. These decisions influence whether the next phase can be added without disruptive rework.

    EPG’s prefabricated IDC approach uses configurable modules and supports expansion as requirements change. This provides a relevant framework for planning capacity in stages. EPG IDC Solution

    Evaluate cooling as part of the power budget

    Electrical and mechanical teams need a shared load schedule. A rack power increase changes the heat that must be removed, while a cooling-system change affects facility electricity demand.

    For compatible equipment, warmer liquid-cooling temperatures can reduce refrigeration demand under suitable site conditions. EPG’s cooling architecture includes secondary inlet temperatures around 45°C, heat recovery and supplementary cooling options. The annual benefit depends on hardware requirements, climate and the selected heat-rejection system. EPG Cooling Solution

    Establish an operable first phase

    Before committing to a capacity milestone, bring the key assumptions into one design review:

    Confirm the electrical supply available on the proposed commissioning date.

    Map rack loads to distribution paths and associated cooling capacity.

    Check usable capacity during planned maintenance and the specified failure scenarios.

    Identify equipment lead times and expansion interfaces that affect the programme.

    Define tests for power transitions, controls and cooling response before IT handover.

    The result should be a clear statement of what the facility can support on day one and what must change before the next expansion.